HomeProjectsPower Project Division

Project Reference List

COAL HANDLING PLANT

Sl. No. Year of Completion Client Project Description
1 2017 (Scheduled) NTPC Limited,Engineering Office Complex,A-8A, Sector-24,Noida-201301,U.P. Coal Handling Plant for Vindhyachal STPP, Stage-V (1x500 MW)
2 Commissioned in 2017 (Scheduled) The West Bengal Power Development Corporation Ltd. 2000 TPH capacity Coal Handling Plant Package for 2x500 MW (Phase-II, Unit- 3 &4) Thermal Power Project at Sagardighi
3 CHP Comissioned in 2016. Rest by 2017 NTPC Limited,Engineering Office Complex,A-8A, Sector-24,Noida-201301,U.P. Coal Handling, Lime Handling and Gypsum Handling Plant for Bongaigaon Thermal Power Station (3x250 MW), Assam
4 2017 (Scheduled) Bharat Heavy Electricals Limited,Bangalore 1000 TPH Coal Handling Plant for Ukai Thermal Power Station (1x500 MW) at Gujarat of Gujarat State Electricity Corporation Limited
5 2014 Durgapur Projects Limited Durgapur, West Bengal. Coal Handling Package for construction of 250 MW extension Unit-8 at DPPS
6 2014 Durgapur Projects Limited Durgapur, West Bengal. Coal Handling Package for construction of 250 MW extension Unit-8 at DPPS
7 Commissioned in 2014 Madhya Pradesh Power Generating Company Limited,Jabalpur Coal Handling Plant for Satpura Thermal Power Station Units # 10 & 11 (2x250 MW) (part of BOP)
8 2013 Bharat Heavy Electricals Limited,Power Sector, 690, Anna Salai, Nandanam, Chennai- 600035 1200 TPH Coal Handling Plant for Bellary Thermal Power Station (1x500 MW) Karnataka of Karnataka Power Corporation Limited
9 2011 Neyveli Lignite Corporation Limited, Neyveli 820 TPH Lignite and LimeStone Handling System Package for Barsingsar Thermal Power Project (2x125 MW) at Rajasthan
10 2011 Vedanta Alumina Limited,Mumbai Coal Handling Plant for 9x135 MW CPP and 4x600 MW IPP at Jharsuguda
11 2008 Durgapur Projects Limited Durgapur, West Bengal. 1000 TPH Coal Handling Plant for Extension Unit #7 (1 x 300 MW) in Durgapur Projects Power Station.
12 2008 West Bengal Power Development Corpn. Ltd., Kolkata. 800 TPH Coal Handling Plant for Sagardighi Thermal Power Station (2 x 300 MW).
13 2007 West Bengal Power Development Corpn. Ltd., Kolkata. 800 TPH Coal Handling Plant for Santaldih Thermal Power Station (1 x 250 MW).
14 2007 Damodar Valley Corporation, Kolkata. 800 TPH Coal Handling Plant for Chandrapura Thermal Power Station
15 2007 National Thermal Power Corporation Ltd., Noida, U.P. 1600 TPH Coal Handling Plant for Ramagundam STPP, Stage-III (1 x 500 MW).
16 2002 ABB Alstom Power India Ltd., New Delhi. 600 TPH Lignite Handling Plant for 1 x 250 MW Neyveli Zero Unit.
17 2001 West Bengal Power Development Corpn. Ltd., Kolkata. 800 TPH Coal Handling Plant for Bakreshwar TPS 3 x 210 MW.
18 1999 CESCLtd., Kolkata. 960 TPH Coal Handling Plant for Budge Budge Thermal Power Station (2x250MW)
19 1998 Andhra Pradesh State Electricity Board, Hyderabad. 1200 TPH Coal Handling Plant (Sec.-I) Track Hopper Package for Kothagudam T.P.S. Stage-V.
20 1995 National Thermal Power Corpn. Ltd., New Delhi. 1600 TPH Coal Handling Plant for Talcher Super Thermal Power Project.
21 1995 Andhra Pradesh State Electricity Board. 600 TPH Coal Crushing & Conveying Plant at Vijaywada T.P.S.
22 1995 Andhra Pradesh State Electricity Board. 1200 TPH Coal Handling Plant (Sec.-I) for Vijaywada T.P.S. (Stage-III).
23 1994 Hirakud Power Co. Ltd. 350 TPH Coal Handling Plant.
24 1992 Neyveli Lignite Corpn. Ltd. Neyveli, Tamil Nadu. 2800 TPH Lignite Handling Sys-tem Extension for Neyveli 2nd Thermal Power Station.
25 1987 Engineering Projects (I) Ltd., New Delhi. 500 TPH Coal Handling Plant for Badarpur Thermal Power Plant.
26 1984 Maharashtra State Electricity Board, Mumbai. 500 TPH Coal Handling Plant for Chandrapur Thermal Power Plant.
27 1983 Renusagar Power Co. Ltd., Renusagar. 600 TPH Coal Handling Plant at Renusagar.
28 1981 Tamil Nadu Electricity Board, Chennai. 2000 TPH Coal Handling Plant for Tuticorin Thermal Power Station.
29 1978 West Bengal State Electricity Board, Kolkata. 500 TPH Coal Handling Plant for Bandel Thermal Power Station.
30 1978 Engineering Projects (I) Ltd., New Delhi. 400 TPH Coal Handling Plant at Amarkantak for MPEB Thermal Power Plant.
31 1978 Engineering Projects (I) Ltd., New Delhi. 350 TPH Coal Handling Plant at Bongaigaon for ASEB Thermal Power Plant.
32 1973 Damodar Valley Corporation, Kolkata. 750 TPH Coal Handling & Blending Plant for Chandrapura Thermal Power Station.
33 1970 Delhi Electric Supply Undertaking, Delhi. 450 TPH ROM Coal Handling Plant extension at Delhi.
34 1968 Govt. of Orissa, Talcher Thermal Power Station. 800 TPH Coal Handling Plant including ROM Coal Cross Country Conveying, Handling & Stockpiling System at Talcher.
35 1968 Delhi Electric Supply Undertaking, Delhi. 450 TPH ROM Coal Handling Plant at Delhi.

WATER DISTRIBUTION/ TREATMENT PLANTS

Sl. No. Year of Completion Client Project Description
1 2018 (Scheduled) NTPC Ltd., Noida, U.P. CW system & Make- up Water system Civil works Package for Nabinagar STPS (3x660 MW)
2 2018 (Scheduled) NTPC Ltd., Noida, U.P. Water Pre -treatment Plnat Package at Barh Thermal Power Project (2x500 MW)
3 2017 (Scheduled) DVC Pre-treatment plant for Bokaro WTP project
4 2017 (Scheduled) NTPC Ltd., Noida, U.P. Ash Water Recirculation & Treatment system package for Singrauli STPS,Stage- I & II ( 5x200 MW + 2x500 MW)
5 2017 Kolkata Municipal Corporation 3 MGD pumping station
6 2017 NTPC Ltd., Noida, U.P. Water Pre-treatment Plant Package for Vidhyachal STPP, Stage-IV (2x500 MW)
7 2017 NTPC Ltd., Noida, U.P. Water Pre-treatment Plant Packagr for Mauda Thermal Power Project (2x500 MW) Stage-II
8 2016 NTPC, Rihand Supply and Installaction of Water Pre - Treatment Plant package for Rihand Super Thermal Power Project, Stage II ( 2X660 MW)
9 2016 Steel Authority of India Ltd.- IISCO Steel Plant,Burnpur-713325 External Water supply System for B.O.F. and C.C.P. for Expansion of IISCO Steel Plant,Burnpur.
10 2014 NTPC-BHEL Power Project Private Limited DM Plant Package for 2x 363.3 MW CCPP for OTPC, Tripura
11 2014 NTPC-BHEL Power Project Private Limited Clubbed water Package for 2x 363.3 MW CCPP for OTPC, Tripura
12 2014 NTPC, Mauda Mauda Super Thermal Power Project (2 X 500 MW), Stage-I, Water Pre treatment Package
13 2006 Rajasthan Urban Infrastructure Development Project, Rajasthan. Providing, laying, jointing, testing and commissioning of sanitary sewers in various colonies of Sanganer Area, Jaipur.
14 2006 Rajasthan Urban Infrastructure Development Project, Rajasthan. Providing, laying, jointing, testing and commissioning of sanitary sewers in various colonies of Amber Area, Jaipur.
15 2005 Hindustan Zinc Ltd 210 TPH Lead Zinc Beneficiation Plant for Rampur Agucha
16 2005 Rajasthan Urban Infrastructure Development Project, Rajasthan. Providing, Laying, Testing and Commissioning of Distribution System and Rising/Gravity Mains in Ajmer City, Rajasthan.
17 2005 Rajasthan Urban Infrastructure Development Project, Rajasthan. Providing, Laying, Jointing & Commissioning of various sizes of Pipe Lines in Jodhpur City, Rajasthan.
18 2004 Tamilnadu Water Supply and Drainage Board, Chennai, Tamilnadu. C.W.S.S. to 674 Rural Habita-tion in Manappanai and Marun-gapuri Unions and Ponnampatty RTP in Trichy District.
19 2004 Ahmedabad Municipal Corporation, Ahmedabad. M.S. & D.I. Pipeline Project for connecting existing water distribution stations and new (pro-posed) water distribution stations to Kotarpur Water Works by Trunk Main.
20 2004 Indian Aluminium Company Limited, Kolkata. Raw Water Piping, Intake Chamber and Associated Work for 100 MW Expansion of Power Plant – Unit #2 at Hirakud, Sambalpur, Orissa.
21 2003 Neyveli Lignite Corporation Ash Water Recirculation & Treatment system package for NLC
22 2001 NMDC Design and Supply of HDPE Slurry Pipeline

BALANCE OF PLANT

Sl. No. Year of Completion Client Project Description
1 2017 (Scheduled) Singareni Collieries Company Limited Balance of Plant Package for Singareni Thermal Power Project(2x600 MW) at Pagedapalli
2 2017 (Scheduled) WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LTD. CONSTRUCTION OF 132/33 KV GI SUBSTATION AT DOMKAL, DISTRICT-MURSHIDABAD AND 2 NOS. 132 KV GI FEEDER BAYS AT NAZIRPUR 132 KV SUBSTATION.
3 Comissioned 2017 POWER GRID CORPORATION OF INDIA LTD. SUB-STATION PACKAGE - S1 FOR 400KV SALEM POOLING STATION, MADHUGIRI, KHAMMAM AND NELLORE POOLING STATION. (SWITCHYARD)
4 2017 (scheduled ) Madhya Pradesh Power Generating Company Limited,Jabalpur Balance of Plant Package for Satpura Thermal Power Station,Ext. of Unit 10&11(2x250 MW)
5 2013 Ideal Energy Projects Limited,Nagpur Balance of Plant Package for Bela TPS (1x270 MW)

ASH HANDLING PLANT

Sl. No. Year of Completion Client Project Description
1 2017 (Scheduled) NTPC Limited,Engineering Office Complex,A-8A, Sector-24,Noida-201301,U.P. Ash Handling & Ash water Recirculation System for Kudgi STPP, Stage-I(3x800 MW)
2 2017 (Scheduled) NTPC Limited,Engineering Office Complex,A-8A, Sector-24,Noida-201301,U.P. Ash Handling System and Ash Water recirculation Package for Mouda Super Thermal Power Project, Stage-II (2x660 MW)
3 2017 (Scheduled) Bhavnagar Energy Company Limited Ash handling & disposal system for 2x250 MW Lignite based Thermal Power project at Bhavnagar
4 2016 Vedanta HCSD system for 3x660 MW Power Plant at Talwandi Sabo
5 Comissioned 2016 National Thermal Power Corporation Ltd., Noida, U.P. Ash Handling Plant for Bongaigaon Thermal Power Project (3x250 MW)
6 2016 Comissioned DVC Bokaro "B" Combined Ash Slurry Disposal System 3x210 MW "B" & 1x600 MW "A" , Bokaro TPS.
7 2014 Essar Power Limited Ash Handling system for Mahan Thermal Power Station (2x600 MW)
8 2013 Crescent Power Limited Dense phase Conveying pipelines, Fly Ash Silo, Dry & wet Unloading & HCSD system for 40 MW TPP at Sarishathali, Asansol
9 2012 Essar Power Limited Ash Handling system for Salaya Thermal Power Station (2x600 MW)
10 1009 Bharat Heavy Electricals Limited Ash Handling Plant for Mejia Thermal Power Station (2x500 MW)
11 2009 Neyveli Lignite Corpn. Ltd. Neyveli, Tamil Nadu. Pneumatic Dense Phase Ash Handling Plant for 2x250 MW Circulating Fluidizec based Combustion Boiler for Neyveli Thermal Power Station-II
12 2009 N.T.P.C., Rihand, U.P. Ash Handling System for, 2 x 500 MW Rihand STPP.
13 2009 Neyveli Lignite Corpn. Ltd. Neyveli, Tamil Nadu. Dense Phase Pneumatic Fly Ash handling system for Neyveli TPS-II (7x210 MW)
14 2008 BAEKDOO INDUSTRIES CO. LTD., Hwaseong-Si,Gyunggi-do, South Korea Design & Supply of critical equipment for the Ash Handling Plant for 2x500 MW Boryeong Thermal Power Plant and 2x870 MWYoung Hung Plant at South Korea
15 2007 Jindal Stainless Limited,Orissa Ash Handling System for at Dhubri,Orissa
16 2007 N.T.P.C., Rihand, U.P. Ash Handling System for Stage-II, 2 x 500 MW Rihand STPP.
17 2006 Maharashtra State Electricity Board, Mumbai. Ash Handling system with HCSD sytem for new Parli TPS (1x250 MW),Unit-I
18 2006 Gujarat Mineral Develop-ment Corporation Limited, Ahmedabad Ash Handling System for 2 x 125 MW Akrimota Power Station.
19 2005 N.T.P.C., Singrauli, U.P. Integrated Ash Disposal System.
20 2004 C.E.S.C. Budge Budge W.B. High Concentrated Slurry Disposal System.
21 2003 Hindustan Paper Corpn. Ltd., Nagaon Paper Mill, Assam. Dense Phase Ash Handling System.
22 2003 NALCO, Orissa. Ash Handling System for CPP 8th Unit.
23 2003 Neyveli Lignite Corpn. Ltd., Neyveli For 2 x 210 MW TPS – 1 Expn. 25 TPH Bottom Ash Handling 32 TPH Dense Phase Pneumatic Conveying with Ash Slurry and Ash Water Recovery System.
24 2002 National Thermal Power Corpn., New Delhi. 4 x 60 MW + 2 x 110 MW Talcher TPS – Ash Water Recovery System.
25 2002 Punjab State Electricity Board, Patiala. Extension of Existing Ash Slurry, Plant Drainage and Sludge Pipe Line at GHTP, Lehra Mohabbat, Bhatinda.

SOLAR POWER PLANT

Sl. No. Year of Completion Client Project Description
1 2018 (Scheduled) Andhra Pradesh Power Generation Company Limited (APGENCO). 100 MW grid connected Solar PV Power Project at Talaricheruvu (V), near Tadipatri for APGENCO.